    PHYSICAL & FINANCIAL STATUS OF MLAADS IN RESPECT OF 28 GOSSAIGOAN LAC
    (Financial Year 2018-2019)
    Sl. No. Name of Scheme Implementing Agency Sanctioned amount Amount released Balance amount to be released Physical Progess% Remarks
    1 2 3 4 5 6 7 8
    1 Constn. of RCC Culvert 1 No with both side approach road at no 2 Howriapet near bell bandh. BDO Kachugaon Dev. Block 5.5 5.5 0 100% Completed
    2 Constn. of road from Tamarhat D.K.road to Sarpomari Black topping road with RCC culvert 2 nos. BDO Hatidhura Dev. Block 7 7 0 100% Completed
    3 Constn. of Burachara river bandh at Burachara village. BDO Kachugaon Dev. Block 6 6 0 100% Completed
    4 Constn. of Hajar bandh at Daikorguri village. BDO Kachugaon Dev. Block 5 5 0 100% Completed
    5 Constn. of road with RCC culvert 1 no at Gwjwnpuri village near Prithiraj House. BDO Gossaigaon Dev. Block 5 5 0 100% Completed
    6 Constn. of road with sand gravelling from Suribari village road to Mothmbil village. BDO Kachugaon Dev. Block 3 3 0 100% Completed
    7 Constn. of road with sand gravelling from Grace E.M.School at Bollamjhora village link road. BDO Kachugaon Dev. Block 4 4 0 100% Completed
    8 Constn. of village connecting road from Bilwguput culvert Khagrabari to Mandaria adivasi village. BDO Kachugaon Dev. Block 3 3 0 100% Completed
    9 Constn.of RCC Culvert 1 No on Kusumbil village road at Kusumbil. BDO Kachugaon Dev. Block 4 4 0 100% Completed
    10 Constn.of RCC Culvert with both side approach road at Burichattam near Nujrul house. BDO Kachugaon Dev. Block 6 6 0 100% Completed
    11 Constn. of road from Kamarpara road to Mannan house with RCC Culvert 1 no at Padmabil. BDO Gossaigaon Dev. Block 3 3 0 100% Completed
    12 Onstn. Of RCC Culvert 1 no and Iron gate at Inter church cemetery (Cremation Ground) at Padmabil. BDO Gossaigaon Dev. Block 5 5 0 100% Completed
    13 Constn. of Mathauri bandh from Kaimmati to West Bengal Border at Kaimmati. BDO Hatidhura Dev. Block 4 4 0 100% Completed
    14 Constn. of road with sand gravelling from Ballamguri near Abul Karim house to Bhomrabil link road. BDO Kachugaon Dev. Block 3 3 0 100% Completed
    15 Constn. of road with earth filling and sand gravelling from Burichattam no 1 near Moinal house to south polashguri boundary. BDO Kachugaon Dev. Block 6 6 0 100% Completed
    16 Constn. of RCC Culvert with both side approach road on chandrapur village road. BDO Hatidhura Dev. Block 5.5 5.5 0 100% Completed
    17 Constn. of road with sand gravelling from Benjamin Lakra house to Public Dong near Hasmat Ali house at No.1 Sapkata. BDO Kachugaon Dev. Block 5 5 0 100% Completed
    18 Constn. of Batabari Shyamdasguri village road at Batabari. BDO Kachugaon Dev. Block 3 3 0 100% Completed
    19 Constn. of village road at South East Raimona Uraon Bosti. BDO Kachugaon Dev. Block 4.5 4.5 0 100% Completed
    20 Constn. of Agriculture canal at Matiapara. BDO Kachugaon Dev. Block 2.5 2.5 0 100% Completed
    21 Constn. of RCC box culvert in front of Khokshaguri MV School at Khokshaguri. BDO Kachugaon Dev. Block 9.7 9.7 0 100% Completed
          99.7 99.7 0 100% Completed

    29 - Kokrajhar West

    PHYSICAL & FINANCIAL STATUS OF MLAADS IN RESPECT OF 29-KORAJHAR WEST (ST) LAC
    (Financial Year 2018-2019)
    Sl. No. Name of Scheme Implementing Agency Sanctioned amount Amount released Balance amount to be released Physical Progess% Remarks
    1 2 3 4 5 6 7 8
    1 Const.of bamboo bridge at Kumguri BDO,Gossaigaon 2.50 2.5 Nil 1 Fund release under process
    2 Const.of Sabitri Agril Bund at Modati -do- 4 4 Nil 1 Fund release under process
    3 Earth filling & Sand gravelling of road from Sonasri house to Army house at Ward No.3,Gossaigaon Rajapara -do- 3 2.25 0.75 0.75 Progress report received & under process
    4 Channel cutting for diversion of Gangia river at Golaipara(Surjyakata) BDO,Dotma 2.5 1.875 0.625 0.75 Progress report not received
    5 Const.of road at Mudhupuri village -do- 2 2 Nil 1 Completed
    6 Const.of Ahila road at Goibari -do- 2 2 Nil 1 Completed
    7 Const.of Chilarai Bhawan at Serfunguri -do- 5 3.75 1.25 0.75 Progress report & under process received
    8 Const.of road at Dingaon village -do- 4 4 Nil 1 Completed
    9 Const.of road at Hel village -do- 1 0.75 0.25 0.75 Progress report received
    10 Const.of 2 Nos. of RCC Culvert at Nepalpara village -do- 2.5 1.875 0.625 0.75 Progress report received & under process
    11 Spreading of sand gravelling at near jogdai Bazar road -do- 3.5 2.625 0.875 0.75 Progress report received
    12 Const.of Panbari Agril Bundh at Panbari BDO,Kachugaon 2 2 Nil 1 Completed
    13 Const.of Telkonga Agril Bundh at Thaigirguri -do- 2.5 2.5 Nil 1 Completed
    14 Const.of Digdari Agril Bundh at Binyakata -do- 3 3 Nil 1 Completed
    15 Const.of Agril Bundh at Joyma village -do- 2 2 Nil 1 Completed
    16 Const.of Bamboo bridge at Bwirali river at Jiaguri -do- 2 Nil 2 0 A/A stopped due to MCC
    17 Const.of Boundary Wall nearby AASA Office at Kachugaon Bazar -do- 2.5 1.875 0.625 0.75 Progress report & under process received
    18 Const.of Kachugaon Nepali Basti road -do- 2 2 Nil 1 Completed
    19 Const.of Gardenpur Agril Bundh -do- 2 2 Nil 1 Completed
    20 Impt.of Jontro Bundh at No.1 Habrubari(Goibari) BDO,Dotma 1 0.75 0.25 0.75 Progress report received
    21 Imtp.of Ahela Rangila raod at Goibari village -do- 1 1 Nil 1 Completed
    22 Imtp.of Mwina Bundh at Shyamthaibari village -do- 1 1 Nil 1 Completed
    23 Impt.of Bonda bundh at Hogmabil Boro Basti -do- 1 1 Nil 1 Completed
    24 Earth filling in front of Shyamthaibari Roy Basti LP School (EU) -do- 1 1 Nill 1 Completed
    25 Impt.of Kujrabguri village road -do- 2 1,50 0.5 1 Fund release under process
    26 Impt.of Dingaon Mushlimpara village road -do- 1 0.75 0.25 1 Fund release under process
    27 Impt.of Gorom Canal at Shyamdharpara village -do- 1 0.75 0.25 0.75 Progress report not received
    28 Impt.of Agriln bund at Boragari village -do- 1 0.75 0.25 0.75 Progress report not received
    29 Earth filling of Football field at Boragari village -do- 1 0.75 0.25 0.75 Progress report not received
    30 Impt.,of Mukhigaon village road -do- 1 1 Nil 1 Completed
    31 Earth filling of damage Fishery Tank at Saktiashram near PWD F/S road -do- 1 1 Nil 1 Completed
    32 Dotma-Sapatgram PWD road to Sankarpara ME School -do- 1 0.75 0.25 1 Fund release under process
    33 Impt.of road Biswanath Pandukon house to Hindi School -do- 1 0.75 0.25 0.75 Progress report received & under process
    34 Earth filling in front of Kotpara LP School -do- 2 1.5 0.5 0.75 Progress report received & under process
    35 Impt.of village road at Koraitola M.Para -do- 1.7 1.7 Nil 1 Completed
    36 Earth filling of Ashoka road at Dumariguri -do- 1 0.75 0.25 1 Fund release under process
    37 Earth filling of Nowervita village road -do- 1 Nil 1 0 A/A not issued due to MCC
    38 Impt.of village road at North Narayanpur village BDO,Kachugaon 1 1 Nil 1 Comlpited
    39 Const.of Waiting Shed a Labra Bazar -do- 2 2 Nil 1 Completed
    40 Impt.ofm Gaobura Santa Office building at Kachugaon -do- 2 1.5 0.5 1 Fund release under process
    41 Impt.of Irrigation Canal at Sejari village -do- 1 Nil 1 0 A/A stopped due to MCC
    42 Impt.of Kawaimari village road -do- 1 1 Nil 1 Completed
    43 Impt.of Jiaguri village road -do- 1 1 Nil 1 Completed
    44 Earth filling at Rimijhimi Ghop Ghonapara Village road as Pt-1. BDO Gossaigaon 1 Nil 1 0 A/A stopped due to MCC
    45 Protection of Rimijhimighop Village from the erosion of the Gongia river with bamboo perquopine at Rimijhimi. BDO Gossaigaon 2 Nil 2 0 A/A stopped due to MCC
    46 Impt.of village road at Bamunkura BDO Kachugaon 1 1 Nil 1 Completed
    47 Impt.of Bumka Agril Bund at Bhumka village BDO,Gossaigaon 2 1.5 0.5 1 Fund release under process
    48 Earth filling in front of Kartimari L.P.School at Kartimari village -do- 1 0.75 0.25 1 Fund release under process
    49 Earth filling of bridge approach at Tulshibil Bhumka P.W.D. road at Tengarvita Village -do- 2 1.5 0.5 1 Fund release under process
    50 Impt.of Kodomguri village road -do- 1 0.75 0.25 1 Fund release under process
    51 Earth filling at Field nearbySankar Aajan Jatiya Bidhyapith at Tulshibil -do- 2 1.5 0.5 1 Fund release under process
    52 Impt.of Hyder Ali road at Balapara village -do- 1 Nil 1 1 Fund release under process
    53 Impt.of village road at Dudumari -do- 2 1.5 0.5 1 Fund release under process
    54 Const.of Tulshibil Thanshree Mahila Buyakota Samaby Samity Ltd. -do- 2 1.5 0.5 1 Fund release under process
    55 Earth filling at Moinatoli L.P.School at Moinatoli -do- 1 0.75 0.25 1 Fund release under process
    56 Impt.of road Uttam Biswas house to Chariali – Kusumbil Pt.II village -do- 1 Nill 1 1 Fund release under process
    57 Earth filliing at Bhawraguri Dhaan Bazar -do- 1 0.75 0.25 1 Fund release under process
    58 Impt.of canal at Chakma -do- 1 0.75 0.25 0.75 Progress report not received

    30 - Kokrajhar East

    PHYSICAL & FINANCIAL STATUS OF MLAADS IN RESPECT OF 30-KORAJHAR EAST (ST) LAC
    (Financial Year 2018-2019)
    Sl. No. Name of Scheme Implementing Agency Sanctioned amount Amount released Balance amount to be released Physical Progess% Remarks
    1 2 3 4 5 6 7 8
    1 Const.of culvert at Kumguri village C/O Raju Chouhan of Kumguri village BDO,Kokrajhar 3 2.25 0.75 75% UC, Progress report received & under process
    2 Const.of waiting shed near Engineering college under Dhauliguri GP -do- 1.00 Nil 1 0% Estimate not received
    3 Sand gravelling at Daloabari village road -do- 4.00 4 Nil 100% Completed
    4 Const.of Mwdwi bhandar bundh at Mestabari. -do- 3.00 3 Nil 100% Completed
    5 Construction of Culvert at Old Amguri Village -do- 5.00 5 Nil 100% Complited
    6 Construction of Culvert at Tulupara village -do- 3.00 3 Nil 100% Fund release under process
    7 Consttruction of Box culvert at odalguri Village road -do- 3.00 2.25 0.75 75% UC, Progress report not received from BDO
    8 Construction of Culvert at Karigaon Village -do- 5.00 5 Nil 100% Complted
    9 Construction /Land Development near VCDC office at Bangaldoba village -do- 5.00 5 Nil 100% completed
    10 Construction of Culvert at Medhipara Village -do- 3.00 2.25 0.75 100% Fund release Under process
    11 Construction of Culvert at Ulubari village Road -do- 4.00 3 1 100% Fund release under process
    12 Development of Tilapara to Medhipara Village Road -do- 5.00 3.75 1.25 100% Fund release under process
    13 Construction of 1(one) RCC culvert near No.2 Amguri L.P. School at Village No.2 Amguri -do- 6..00 4.5 1.5 75% UC, Progress report not received from BDO
    14 Construction of Village Road at Harinaguri Village C/O Kasem Ali -do- 5.00 5 Nil 100% Completed
    15 Construction of Culvert at Pradip Soren house to Kokrajhar Tea Estate -do- 4.00 3 1 75% UC, Progress report received from BDO
    16 Construction of Village Link Road at Balapara Village, Titlanguri -do- 1.00 0.75 0.25 75% UC, Progress report received & under process
    17 Construction of RCC Box Culvert at Gopalgaon Village BDO,Dotma 3 3 Nil 100% Completed
    18 Construction of RCC Slab Culvert at Kamarpara Village -do- 7.00 5.25 1.75 75% UC, Progress report received & under prcess
    19 Development of Jibou Bundh at Shialmari -do- 2.00 1.5 0.5 75% UC, Progress report received & under process
    20 Construction of RCC Box Culvert at Bhabanipur Cemetry BDO,Kokrajhar 6 .6.00 Nil 100% Completed
    21 Construction of Sewari Bilw Bundh with earth filling at Nakargaon BDO,Dotma 1 1 Nill 100% Completed
    22 Construction of Swithw Longa Bundh at Jhorsimlaguri -do- 2.00 2 Nil 100% Completed
    23 Construction of Alsia Bwrai Jamphwi at paddy field of Hiramba Basumatary -do- 2.00 2 Nil 100% Completed
    24 Construction of Funga Bundh at premnagar Rabha Bosti BDO,Kokrajhar 2 Nil 2 0% A/A stopped due to MCC
    25 Sand Grvelling of Magurmari Bylane to Jilimili Playground at Magurmari village -do- 2.00 2 Nil 100% completed
    26 Const. of RCC Box culvert at Narabari near Gala Goyari house -do- 2.00 2 Nil 100% Completed
    27 Const./Earth filling and sand gravelling of West Maligaon village road C/O Birsen Soren -do- 3.00 3 Nil 100% Completed
    28 Const.of waiting shed at Batabari village cemetry -do- 2.70 2.7 Nil 100% Completed
    29 Const.of culvert at Baroghar under Daloabari Tea Estate -do- 2.00 1.5 0.5 100% Fund release under process
    30 Land Development of Tinklanguri LP School compount -do- 1.00 Nil 1 0% A/A stopped due to MCC
    31 Protection bundh at Bhaoraguri(Pategaon) BDO,Dotma 2 1.5 0.5 75% UC, Progress report not received from BDO